SL. No. | Nature of Work | Date of Tender | Estimated Value of Tender | No. of Tenders who had Applied | Name of successful contractors | Date of Awarding the work | Estimated life of the complted project | Total amount paid to the contractor | Date of Completion of Work | Penaltied levied for the Delay | The Period Delay |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | PAINTING WORKS OF EXPOSED PORTION OF RISING MAINS OF WAZIRABAD WATER WORKS | 4.08.2010 | Rs.197597/- | 2 Nos. | M/s Sanjay Sales Corporation | 13.08.2010 | 12 Months | Yet to be paid | 16.09.2010 | Not Applicable | NIL |
2 | WATER TREATMENT PLANT | 24.06.2008 | On L.S basis being DBO project | 3 Nos. | VA Tech Wabag Limited | 10.09.2008 | 50 years for civil & 15 years for E&M works | 24.98 Crores | 19.09.2010 | Case for extension of time is in process. | Case for extension of time is in process. |
3 | REPARING / DANTING /PAINTING / OF TATA TRUCK NO. DL1GB-3912 MODEL S1316 AT CHANDRAWAL | 11.08.10 | Rs.29136/- | 2 Nos. | M/S Kamlesh Engg.works | 3.092010 | 3-4 year | yet to be paid W.O amount Rs 28575/- | under exetution | NIL | NIL |
4 | CONSTRUCTION OF 1 MGD (4.54 MLD) STP USING MEMBRANE BIO-REACTOR (MBR) TECHNOLOGY FOR RECIRCULATION / REUSE OF TREATED EFFLUENT FOR COMMON WEALTH GAME VILLAGE. | 23.06.2008 | Rs.31.95 crores | 3 Nos. | M/s UEM INDIA LTD & GL&V INDIA PVT LTD | 16.10.2008 | 30 years (designe period) | Rs.20.56 crore | 19.06.2010 | The extension of time is under consideration on the merit of the case. | 4 months |
5 | CONSTRUCTION OF 1 MGD (4.54 MLD) STP USING MEMBRANE BIO -REACTOR (MBR) TECHNOLOGY FOR RECIRCULATION / REUSE OF TREATED EFFLUENT FOR COMMON WEALTH GAME VILLAGE. | 23.06.2008 | Rs 31.95 crores | 3 | M/s UEM INDIA LTD & GL&V INDIA PVT LTD | 16.10.2008 | 30 years (design period) | Rs 20.56 crores | 19.06.2010 | The extension of time is under consideration on the merit of the case. | 4 months |
6 | Water Treatment Plant | 24.06.2008 | on L.S basis being DBO project | 3 Nos. | VA TECH Wabg Limited | 10.09.2008 | 50 years for civil & 15 years for E&M works | Rs. 24.98 crores |
19.06.2010 (plant was put into operation) |
Case for extension of time is in process. | Case for extension of time is in process. |
7 | Construction of 1 MGD (4.54 MLD ) STP using Membrance Bio-Reactor (MBR)technology for recirculation / reuse of treated effluent for common wealth game village. | 23.06.2008 | Rs. 31.95 crores | 3 Nos. | M/s UEM INDIA LTD & GL&V INDIA PVT LTD | 16.10.2008 | 30 years(design period) | Rs. 20.56 crores | 19.06.2010 | The extension of time is under considerati on the merit of the case | 4 months |