Procedure followed in decision-making process

Home/ Procedure Followed In Decision-making Process

MANUAL 3
PROCEDURE FOLLOWED IN DECISION-MAKING PROCESS
[SECTION 4(1)(B)(III)]

The procedure can be described both in narrative form and through Flow Process Chart. In narrative form the stages through which a proposal passes, the levels at which it gets examined and the final authority towhich it has to go for approval may be explained.
Flow Process Chart for issue of Water Connection

S.N Activity Level of action Time Frame
1 ZE to receive application and put a diary number Dealing Clerk Same day
2 To sent new water connection file/ application to concerned ZRO Head Clerk/Allotment clerk 2 days
3 To visit premises of applicant by area JE and sanction of connection by ZE on receipt of file from ZRO JE 3 days
4 To allot connection and issue bill Allotment clerk 1 Day
5 To accord boring permission by ZE JE 1 Day
6 Procedure followed in the decision making process,including channels of supervision and accountability of Revenue .